Keystone XL Certificate Expires In South Dakota

Published 07/02/2014, 03:44 PM
Updated 07/02/2014, 04:00 PM
Keystone XL Certificate Expires In South Dakota
TRP
-

By Maria Gallucci - The long and bitterly contested attempt to build the Keystone XL pipeline from Canada to the Gulf of Mexico just received another setback.

A certificate allowing TransCanada Corporation (TO:TRP) to construct the pipeline through South Dakota lapsed over the weekend, meaning the company will have to reapply for permitting. The process is sure to draw fierce opposition from environmental groups that argue the project will endanger water supplies and exacerbate global warming, as well as landowners who object to construction on their property.

South Dakota’s Public Utilities Commission approved the project on June 29, 2010, by issuing a certificate that placed certain conditions on the project. Four years later, TransCanada will have to prove that it can still meet those conditions.

An evidentiary hearing will be held once TransCanada applies to recertify, Gary Hanson, chairman of the South Dakota utility regulator, told the Financial Post. “I would anticipate that there will be challenges … by a number of organizations and possibly citizens.”

© TransCanada. Keystone XL pipeline route if built.

TransCanada spokesman Davis Sheremeta told the publication in an email that the company is “waiting to determine exactly what will be required by the South Dakota PUC” before it reapplies for certification. “We are pulling everything together and will submit our recertification in due course.”

The Keystone XL pipeline would carry tar sands crude oil over 1,700 miles, starting in Canada’s Alberta province and ending at refineries in Texas. TransCanada completed the pipeline’s southern leg, a 487-mile stretch from Cushing, Oklahoma, to Nederland, Texas, earlier this year, and oil is already flowing from the $2.3 billion segment.

Keystone Map

But the Alberta-to-Nebraska component remains mired in legal and permitting challenges. Since the northern leg crosses an international border, the U.S. State Department must approve it, although President Barack Obama is expected to make the final call. The Obama administration says further review is still needed to determine the full scope of the pipeline’s environmental and economic impacts. And in April, it said it would delay a decision on the Keystone XL until a legal fight is resolved in Nebraska.

A state district court in February invalidated the pipeline’s route through Nebraska, striking down a state law that would have let TransCanada and Gov. Dave Heineman avoid regulators in locating a 300-mile segment in Nebraska. The state attorney general is appealing the judge’s ruling.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.