Reuters
Published Sep 06, 2022 07:39PM ET
Updated Sep 06, 2022 09:41PM ET
By Jonathan Stempel
NEW YORK (Reuters) -A U.S. judge said Rio Tinto (NYSE:RIO) Plc must face an investor lawsuit accusing the Anglo-Australian mining giant of concealing delays and huge cost overruns at a Mongolian copper and gold mine owned by Turquoise Hill Resources (NYSE:TRQ) Ltd, in which Rio Tinto has a majority stake.
In a 134-page decision made public on Tuesday, U.S. District Judge Lewis Liman in Manhattan said funds advised by Pentwater Capital Management LP, Turquoise's largest minority shareholder with about a 10% stake, may pursue a proposed class action on behalf of Turquoise shareholders from July 2018 to July 2019.
The judge dismissed some claims against Rio Tinto and various executives, and all claims against Montreal-based Turquoise. His decision is dated Sept. 2.
Pentwater accused Rio Tinto and Turquoise of fraudulently assuring that the $5.3 billion Oyu Tolgoi mine was "on plan" and "on budget," even as it was falling up to 2-1/2 years behind schedule and coming in as much as $1.9 billion over budget.
Shareholders of Turquoise said their investments lost close to three-quarters of their value as the truth became known. The shareholders are seeking damages from Rio to recoup their losses.
In letting Chicago-based Pentwater seek to hold Rio Tinto liable for some of Turquoise's statements, Liman cited claims that the companies had an "extraordinarily close relationship," and that Rio Tinto had "near total control" over the mine.
"Plaintiffs do sufficiently allege that Rio knew of delays or cost overruns shortly before the class period and, instead of trying to fix them or disclose them to investors, attempted to silence those who spoke out about them," Liman wrote.
Rio Tinto said Pentwater's claims were unfounded and said it had consistently complied with its disclosure obligations.
"Pentwater's claims are completely without merit, and we are confident that, when all the facts are considered by the court, or if necessary by a jury, Pentwater's claims will be rejected," the miner said in a response to the court decision sent to Reuters.
Turquoise and its lawyers did not immediately respond to requests for comment. Pentwater's lawyer Salvatore Graziano declined to comment.
Earlier this month, Rio Tinto agreed to pay about $3.3 billion for the 49% of Turquoise it does not already own.
Turquoise owns 66% of the Oyu Tolgoi mine, and Mongolia owns the rest.
In January, Rio Tinto and Mongolia settled a long dispute over the mine's economic benefits, in an accord that waived $2.4 billion of debt owed by Mongolia's government.
The case is In re Turquoise Hill Resources Ltd Securities Litigation, U.S. District Court, Southern District of New York, No. 20-08585.
Written By: Reuters
Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.