Ford’s new Tennessee plant aims to build 500,000 electric trucks a year

Reuters

Published Mar 24, 2023 06:07AM ET

Updated Mar 24, 2023 12:23PM ET

By Paul Lienert

STANTON, Tennessee (Reuters) - Ford Motor (NYSE:F) Co plans to build up to 500,000 electric trucks a year at its BlueOval City complex under construction in western Tennessee, the automaker said on Friday.

BlueOval City will assemble several versions of Ford’s next-generation F-series electric pickup, which the company calls Project T3.

In an event Friday at the plant, Ford CEO Jim Farley said production will begin "in roughly 30 months" -- the fall of 2025.

The Stanton plant northeast of Memphis is part of Ford’s plan to have global EV production capacity of 2 million vehicles a year in place by the end of 2026.

A video shown at the event described the new electric pickup as "the sequel to the F150 Lightning" that is currently built near Ford headquarters in Dearborn, Michigan, and is based on the standard combustion-engine F-series pickups.

Ford said BlueOval City will have a general assembly footprint that is 30% smaller than that of a traditional assembly plant, with a higher production capacity. Most current auto plants are designed to build 250,000-300,000 vehicles a year.

Tesla (NASDAQ:TSLA) this month said its future electric vehicle plants will be up to 40% smaller than traditional plants.

Ford's Project T3 pickup is being developed on a new dedicated EV truck architecture.