Electric utility firm The Southern Company’s (NYSE:SO) much delayed clean coal power plant project Kemper in Mississippi has suffered yet another setback. The project has been facing continuous criticism owing to its poor execution, cost overruns and multiple delays.
Recent Updates
Mississippi Power, a subsidiary of Southern Company, recently announced a delay in the projected in-service date of its Kemper County plant until the end of June. The extension of the schedule, will add $22 million to the overall cost of the plant. The company also revealed that it needed to redesign and replace a key component in its plant – syngas cooler super heater system – in order to establish long-term sustained operations. Sustained operations will also require relocation of ash loading process together and other minor improvements. This will add another $164 million to the operating costs of the project. Therefore, the latest glitch would hike the overall cost of the plant by $186 million.
While the company expects the facility to become functional by the end of June, the redesigning of the syngas cooler super heater would need another 18 to 24 months of construction time. Further, the company also intends to undertake additional improvement projects over the next few years to fix leaks and other issues relating to the plant’s performance, safety and operations.
The Kemper Project
Kemper project had been central to ex-President Obama’s Climate Plan as it is based on clean coal. Notably, the project also received the support of President Trump.
The 582-megawatt electric power plant is designed to pipe synthetic gas through a chemical plant to remove carbon dioxide and other chemicals, and then burn the gas in turbines to generate electricity. It is designed to capture up to 65% of carbon dioxide emissions from the plant.
Challenges Galore
The project found it difficult to get its two gasifiers to operate consistently. The plant is already three years behind schedule and is over $4 billion beyond the stipulated budget. The overall cost of the plant was estimated to total to around $3 billion in 2010. However, with several delays adding to the project’s cost, the current price tag of the plant has ballooned over $7.3 billion. In the past 18 months, the company announced 10 delays owing to project management problems.
Further, the additional improvement projects will add to costs and negatively impact certain economic aspects of the Kemper.
The economics of the Kemper project is a major cause of concern for the company as the plant is not competitive at the current natural gas prices. According to the viability analysis undertaken by the Southern Company, the project will be economical with natural gas prices at $5 per million British Thermal units. This seems quite unlikely for many years according to Energy information Administration forecast.
Rate plan Updates
In 2015 Public Service Commission allowed the company a 15% rate hike for the plant’s incremental costs to be passed on to ratepayers.
Though the company was again to file rate plans for the project in early June, it recently announced that there would be no rate increase. The company has planned to keep the current customer rate in place for at least 11 months and has not filed a full-rate review on recovery of the project’s costs. According to the spokesperson of the company, “Its plan to avoid further raising customer rates is likely to reduce whiplash to customers when rates rise later to pay for Kemper, would pay off accumulated costs more quickly and would help the company wean itself off financial support from Southern Co. while maintaining credit ratings.”
Mississippi Power is considering to develop a traditional rate case and a rate mitigation plan to address these costs, however, the timing of that filing is uncertain.
Zacks rank & Key Picks
Southern Company is one of the largest and best-managed electric utility holding companies in the U.S. The firm dominates the power business across the southeastern region.
The utility currently carries a Zacks Rank #4 (Sell). Southern Company’s shares have rallied almost 7% over the last six months, underperforming the Zacks categorized Zacks Investment Research
Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.