As Caledonia Mining (NYSE:CMCL) (CMCL) continues to implement its investment plan (IP), logistical issues governing ore handling volumes and access to higher-grade ore bodies have affected gold production during Q2 and H117.

Underground works to ameliorate material handling bottlenecks have taken place with successful completion, inter alia an underground tramming loop. However, grades are lower due to restricted access to the higher-grade Eroica and Lima ore bodies situated on the other side of the Central Shaft development area to the main surface haulage route, the No. 4 haulage shaft. We have adjusted our valuation to reflect this and the H117 financial results, leading to a valuation of 933p for successful implementation and operation of the Blanket IP.